The Chairman of Ca Mau Provincial People's Committee (PPC) has just requested the PetroVietnam Power Corporation (PV Power) as an investor to urgently complete the necessary documents and procedures for Ca Mau PPC as soon as possible to submit to the Ministry of Industry and Trade (MOIT) for considering.
Starting Ca Mau 3 combined cycle gas turbine project
Starting Ca Mau 3 combined cycle gas turbine project

And additionally approving Ca Mau 3 combined cycle gas turbine (CCGT) project using liquefied natural gas (LNG) in Khanh An Industrial Park, U Minh district into the National Power Development Planning.
 
According to the project document, the 35,000 billon VND Ca Mau 3 power project including CCGTs with a total capacity of 1500 MW, power generation of 9 billion kWh/year and consuming1.2 million tons of LNG per year, expects to be put into operation in 2026-2027, contributing to ensuring power supply for the southern region in the condition that the coal thermal power projects in the region planned to be put into operation in period of 2026 - 2030 should be behind progress.
 
Besides Ca Mau 3 power project, PV Power will also invest in Nhon Trach 3 & 4 CCGTs with a total capacity of 1300 – 1760 MW (by 650-880 MW each) using 1.4 million tons of LNG per year (backup fuel is DO).
 
The total investment capital of these projects estimates about 32,481 billion VND, from which 25% is equity and 75% - loan.
VietnamEnergy

 Gửi ý kiến phản hồi

Họ và tên Email
Tiêu đề Mã xác nhận

News

The new regulations on defining electricity generation prices, the order of checking power purchase agreement

Cập nhật 23/02/2021

The Ministry of Industry and Trade (MOIT) has just promulgated Circular No. 57/2020/TT-BCT (Circular...

Innovation

EVN restructures the dependent accounting units

Cập nhật 07/11/2018

The Prime Minister has just directed Electricity of Vietnam (EVN) to restructure, reorganize and...

Investment

SEACEF to invest in Vietnam wind power

Cập nhật 27/01/2021

Levanta Renewables seeks to open new energy development corridors in Central Highland region ...

Business

EVNNPC given stable outlook by Fitch Ratings

Cập nhật 20/01/2021

The Vietnam Electricity Northern Power Corporation (EVNNPC) was recently assigned a Long-Term Foreign-Currency...

Production

Electricty dispatch centre asks for better infrastructure

Cập nhật 27/01/2021

The National Load Dispatch Center (A0) has asked Vietnam Electricity (EVN) to equip it with better...