Quang Ninh thermal power project falling behind schedule

09/04/2009 16:32:28 - views: 2,506

As revealed by Quang Ninh Thermal Power Joint Stock Company, according to the contract signed with Shanghai Electric Group Company Limited (SEC), the unit 1 of Quang Ninh thermal company project No.1 (300 MW) should have been licensed the Preliminary Acceptance Certificate (PAC) on February 2nd, 2009. However, because the contractor SEC did not keep up with the progress, EVN has allowed SEC extend the deadline of licensing PAC for the unit 1 to October 2009. Still, up to now, the thirty-fourth month, the installation volume of SEC has just reached 73% and the general progress of the project has been about 78% while the approved progress is 93.4%.

As remarked by the Thermal Power Project Management Board No.1, the general progress of Quang Ninh thermal power project No.1 is about 8 months behind schedule, in which the time of switching on the 110 kV switchgear is 13 months progressing slowly, the time of switching on the 220 kV line is 12 months late, the circulation water-pumping station is 2 weeks behindhand, the firing is 1 month slow and so on.

Currently, the activity of resettlement to clear land is still encountering difficulties because the construction of resettlement area is falling behind schedule. There are 3 out of 26 households who do not agree to move out of the site.

The engineering, procurement and construction (EPC) contract for Quang Ninh thermal project No.2 (600 MW) has become effective since June 11th, 2007. This is now the twenty-second month of the contract, but the work volume completed is still too small.

The main reason for that is the lack of workforce. According to Quang Ninh Thermal Power Company, in the final stage of construction of Quang Ninh thermal power project No.1, there is a need of 4,500 employees to retain the progress while this company can only mobilize nearly 2,000 Chinese and 225 Vietnamese. Also, the contractor is constructing the remaining part of Quang Ninh Thermal Power No.1, so there must be a shortage of labour for Quang Ninh Thermal Power No.2.

Quang Ninh Thermal Power Project which is invested by The Electricity of Vietnam and located in Ha Long City has the capacity of 1,200 MW and the total investment of VND 9165.2 billion. The project is implemented by an EPC contract with the contractor SEC. With the annual power output of 3.6 billion kWh/year, Quang Ninh Thermal Power Company, when put into operation, will strengthen the credibility of power supply for the economic triangle of Hanoi – Hai Phong – Quang Ninh.

Thanh Mai

News

ASEAN transitioning towards sustainable energy

Cập nhật 23/11/2020

Renewable energy plays an increasingly important role in the diversification of energy supplies, which...

Innovation

EVN restructures the dependent accounting units

Cập nhật 07/11/2018

The Prime Minister has just directed Electricity of Vietnam (EVN) to restructure, reorganize and...

Investment

Japanese firm invests in big energy project in Khanh Hoa

Cập nhật 19/11/2020

Japanese firm J-Power is taking necessary procedures for the investment of a nearly 3.2 billion USD...

Business

EVN aims to complete key power projects in 2020

Cập nhật 21/10/2020

Vietnam Electricity (EVN) planned to put two turbines of Thuong Kon Tum hydropower plant and Se San...

Production

Power consumption rises as economy recovers from pandemic

Cập nhật 26/10/2020

Power consumption increased significantly in September as the economy started to find its feet after...