The plant has the capacity of 1.89 MW, consists of 3 hydraulic turbines with 630 kW capacity of each. The whole project has been totally invested more than VND 30 billion. The project composes of such categories as main penstock, branch penstock, downstream discharge canal, 22 kV power distribution substation, 22 kV power transmission line and some addition categories. This is a small and medium-sized hydropower project which is constructed in the position of the main canal line. Chinese experts take the responsibilities of machinery installation and running test for major equipments of the Plant.
As planned, the project will be completed in December 2008. After finished, it will produce over 8 million kWh annually. When put into operation, the project will help overcome power shortage in Thai Nguyen province.
Mai Phuong