Total effort, "sprint" to complete the 500kV circuit 3 line

Thứ sáu, 23/8/2024 | 14:36 GMT+7
The national key energy project of 500kV 3-circuit transmission line Pho Noi - Quang Trach is in the sprint stage with the total participation of many forces. According to Vietnam Electricity Group (EVN), this historic project is expected to be inaugurated on the occasion of National Day September 2, expected to increase electricity supply capacity in 2024 and the coming years.

The 500kV circuit 3 line project goes through 9 provinces, including 4 component projects, started in October 2023 and January 2024. Photo: Vo Thanh Vinh

From "transmission soldiers" who traveled 2,000km to the North to carry out construction

Having to go to the construction site of 500kV circuit 3 line projects, witness with my own eyes the small "transmission soldiers" installing columns weighing hundreds of tons, hundreds of meters high, erected in the air. Only on complex terrain can we see how proud their tireless efforts are. That is not only sweat and effort but also shows the high level of expertise, steely spirit and persistent will of the construction forces on the construction site of the 500kV circuit 3 line project.

“The pressure of progress does not allow us to forget the requirements for construction quality. The fastest progress must go hand in hand with the best quality. Many days the weather was erratic, with scorching heat and sudden thunderstorms. The brothers were all wet but still persevered in holding on to the poles. Sweat mixed with rainwater, accompanied by hot steam rising from the ground, made the brothers exhausted as they had to carry hundreds of large, long, heavy iron bars on their shoulders, but they all still rushed towards the goal of reaching the finish line before the deadline." - Mr. Le Duc Tan - Project Commander of Minh Quang Mechanical and Electrical Joint Stock Company talked with Lao Dong Newspaper.

Even though he was 51 years old, when ordered to "generally mobilize" to support circuit 3, Mr. Dang Trinh Sinh - Western Power Transmission Team 2 (Power Transmission Company 4) - did not hesitate to volunteer to go. Having traveled nearly 2,000km, Mr. Sinh and 35 members of the assault unit present in Hai Duong participated in building the column.

“For me, the biggest difficulty is the weather. The heat in the North is much harsher and hotter than in the South. The first days we set foot in the North, we suffered from "heat shock", it took 2-3 days to get used to the climate. Despite difficulties, we still work with our best efforts to complete assigned tasks on schedule," Mr. Dang Trinh Sinh shared.

To the cooperation of thousands of soldiers of Military Region 4

Not only is the total power industry involved, the project also has the cooperation of the military as well as the people of relevant localities. On August 22, Vietnam Electricity Group announced that at the present time, the 500 kV line project of circuit 3 of Pho Noi - Quang Trach route has been energized to the Quynh Luu - Thanh Hoa section. For the remaining section from Nghe An to Quang Trach, construction units are mobilizing total force to complete the remaining work, progress is guaranteed to be completed before September 2.

During this time, the armed forces of Military Region 4 mobilized thousands of officers and soldiers to support the construction of the 500kV line project passing through Nghe An - Ha Tinh. The Command of Military Region 4 directed the Military Commands of the provinces to mobilize officers and soldiers to support the construction of the 500kV circuit 3 line. On August 20, at the construction site of the 500kV line through Nam Dan district , hundreds of officers, soldiers of the standing army and militia and self-defense units and localities of Nghe An province were present to support the National Power Transmission Corporation (EVNNPT) in site clearance and construction. project work. Colonel Tran Vo Viet - Deputy Commander of Nghe An Provincial Military Command directly commands the support force.

Up to this point, the Military Command of Nghe An province has mobilized more than 650 officers and soldiers of the standing army and militia to participate in supporting the construction of the project. In addition to supporting EVNNPT to carry out tasks such as transporting equipment to the construction site, clearing routes, restoring the environment..., officers and soldiers of the armed forces of Nghe An province have mobilized and propagated households. People carry out the Party and State's policies to relocate houses and assets for construction projects.

In Ha Tinh, the Military Command of Ha Tinh province has mobilized officers and soldiers to support construction units of the 500kV circuit 3 line through the area. Accordingly, from August 19 to August 22, about 500 officers and soldiers of the armed forces units in Ha Tinh focused on supporting the transportation of equipment, distributing pine trees, and organizing rope pulling forces. On the first day of deployment on August 19, there were more than 100 officers and soldiers of Regiment 841 and Cam Xuyen district militia supporting construction units in Lac Tho village, Cam Lac commune, Cam Xuyen district. . The contributions of officers and soldiers of the Armed Forces of Military Region 4 have joined forces with the electricity industry to soon complete the 500kV line project according to the assigned plan.

Same progress as the sprint days...

The 500kV circuit 3 line project goes through 9 provinces, including 4 component projects, started in October 2023 and January 2024. Regarding construction, by August 13, 2024, the entire project had completed casting column foundations for 1,177/1,177 locations (reaching 100%); Completed column erection in 1,159/1,177 positions (reaching 98.5%); Completed rope pulling in 321/513 anchorages (reaching 62.5%).

In particular, at 5:30 p.m. on August 19, EVNNPT, the Northern Power Project Management Board coordinated with relevant units to successfully energize 2 circuits of the 500kV 3-segment line project of the Southern Thermal Power Plant. Dinh 1 - Pho Noi, meets the Prime Minister's direction. According to EVNNPT leaders, with the spirit of "just work, don't talk back", "overcome the sun, beat the rain", work "3 shifts, 4 crews", "eat quickly, sleep quickly", engineers, Workers of the units participating in the project worked with the highest spirit and responsibility to bring the project to its destination on time.

At 11:10 a.m., on August 19, EVNNPT, the Central Region Power Project Management Board in coordination with related units also successfully energized the 500kV 3-circuit line project in the Quynh Luu - Thanh Hoa section, responding to Meet the targets directed by the Prime Minister.

Deputy General Director of EVNNPT - Truong Huu Thanh said: During the implementation process, the project always received the attention and direction of the Prime Minister, ministries, branches, and leaders of Vietnam Electricity Group . Along with that is the support of the authorities at all levels where the project passes through, the consensus and joint efforts of the people who have given up land for the project, and participated in supporting the construction phase of digging and casting the foundation. Previously, at 11:48 a.m., June 30, EVN, the Northern Power Project Management Board coordinated with relevant units to successfully energize the 500kV 3-circuit line project in the Thanh Hoa - Nam Dinh section, responding Meets the Prime Minister's direction requirements.

Pay attention and take care of workers constructing the 500kV circuit 3 line project


Member of the Party Central Committee, Chairman of the Vietnam General Confederation of Labor Nguyen Dinh Khang gave gifts to workers at column number 40 in Ky Thinh ward, Ky Anh town, Ha Tinh province. Photo: Tran Tuan

Recently, the leaders of the Vietnam General Confederation of Labor have paid special attention to union members and workers working on the 500kV circuit 3 line project.

On August 21, the working delegation of the General Confederation of Labor of Vietnam and the Electricity of Vietnam (EVN) led by Mr. Nguyen Dinh Khang, Member of the Party Central Committee, Chairman of the General Confederation of Labor of Vietnam visited and gave gifts to workers at the construction site of Quang Thermal Power Plant. Trach - Quang Binh and Quang Trach 500kV transformer station in Quang Dong commune, Quang Trach district.

The Vice Presidents of the Vietnam General Confederation of Labor also paid great attention to the workers working on the construction site when they repeatedly visited the construction site to visit and encourage the workers. On June 9, in Thanh Hoa province, Ms. Thai Thu Xuong - Permanent Vice President of the Vietnam General Confederation of Labor and the working group inspected the implementation of the emulation movement and visited and encouraged union members and workers on the construction site. Quang Trach - Pho Noi 500kV Circuit 3 Line Project. Also in June 2024, Vice Presidents of the Vietnam General Confederation of Labor Huynh Thanh Xuan, Ngo Duy Hieu, Phan Van Anh and Nguyen Xuan Hung along with working delegations came to reward and encourage the units participating in the early energization project at the Component project of 500kV circuit 3 line project.

At the visits, leaders of the Vietnam General Confederation of Labor visited and gave gifts to workers; acknowledged and expressed emotion at the efforts of the units participating in the project to overcome all difficulties and work together to complete the large amount of work set out. To date, the Standing Committee of the Presidium of the Vietnam General Confederation of Labor has organized 8 delegations to directly visit, encourage, and give gifts to workers at 31 work locations throughout the 500kV circuit 3 line project from Quang Trach ( Quang Binh) to Pho Noi (Hung Yen), the amount of money to give gifts is 1.67 billion VND. In addition, the Vietnam General Confederation of Labor decided to support 3,932 billion VND for 3,932 union members, workers and labor officials who were seconded to directly work on project works, the support level is 1 million VND/person. Bao Han

At the meeting on the implementation status of the 500kV 3-circuit line project from Quang Trach (Quang Binh) to Pho Noi (Hung Yen) on August 13, 2024, Politburo member, Prime Minister Pham Minh Chinh stated clearly , up to now the remaining amount of work is not much, but it is difficult work, so relevant agencies, units, localities, and forces must be more determined, make more efforts, try harder, do work more decisively, with more focus and focus in the final sprint phase. With the goal of completing the remaining work, we are determined to inaugurate the entire project on the occasion of the August Revolution and National Day September 2 this year.


 

Source: Laodong