Mai Dong transformer substation, which supplies
electricity for Southern Hanoi, with the flood water going down
In order to meet the demand f electricity in Hanoi, the Company has continuously pumped and cleaned the electrical devices and right away carried out experiments so that the system can be put into operation in the short term.
Up to yesterday’s late afternoon (November 3), seven out of eight 35 kV substations in Ha Dong have already been re-operated. Some others will be recovered as soon as the flood water has gone down.
The task of taking the duties in power transmission units in the North at large and in Hanoi in particular is on the top priority.