Commissioning, energizing and putting into operation the 500kV Duyen Hai Thermal Power – My Tho transmission line project

Thứ sáu, 3/6/2016 | 14:08 GMT+7
​​​Under the close direction by leaders of National Power Transmission Corporation (EVNNPT), support provided by EVNNPT’s functional departments, the determination by Southern Power Projects Management Board (SPMB) and effective cooperation with Power Transmission Company No. 4 (PTC4) and the relevant units, at 4h23 on May 26th 2016, SPMB coordinated with relevant units organize the commissioning, energizing and putting the 500kV Duyen Hai Thermal Power Plant – My Tho transmission line project into operation.

 
The 500 kV Duyen Hai Thermal – My Tho transmission line energizing will connect, receive and evacuate capacity of Duyen Hai Thermal Power Centre to the national power system; exchange power energy with the large power sources to be constructed in the area and increase the stability, reliability for power system; ensure a qualified, uninterrupted power supply for the socio-economic development of the South-Western provinces and surrounding areas.
 
The 500kV Duyen Hai Thermal Power Plant – My Tho transmission line is a double circuit one of 113km length, connecting the switchyard of 500kV Duyen Hai Thermal Power Centre to 500kV My Tho substation. The transmission line route has 241 tower locations run through area of 44 communes, towns, 12 districts of 4 provinces of Tra Vinh, Ben Tre, Vinh Long and Tien Giang. Over 5,000 households are affected, totally 1,427 houses and architectures have to be removed from the right of way; Totally, 144,914m2 land area are permanently acquired by the project, and 674,847m2 land area affected by the right of way.
 
​Total investment cost of project is VND 4,359 billion VND invested by EVNNPT. SPMB manages the project on behalf of EVNNPT; Power Engineering Consultation Company (PECC2) is responsible for project design; Project implementation contractors include Song Da 11 Joint Stock company and Song Da 11 Thang Long one-member liability company , Vietnam Electricity Construction Corporation, Power Construction Company 4 (PCC4), Power Construction Company No. 1 (PCC1), Power Construction Company No. 2 (PCC2). Power Transmission Company 4 (PTC4) takes over the project operation.
 
The project commissioning has been done according to the current regulations, the gained results have met requirements on quality, ensuring the environment hygiene standards.
 
The project commissioning and energizing are gained thanks to the efforts and determination by SPMB’s staff and support by the relevant units.
 
EVNNPT