The projects include the Thai Thuy 220kV transformer station, which is scheduled for completion in December and the 220kV Truc Ninh transformer station, set to go into operation in February, 2017.
The construction of the Thai Binh-Tien Hai-Truc Ninh 220kV transmission line will be finished in April, 2017, while the Truc Ninh 220kV line going through Ninh Binh and Nam Dinh will be started in December and be completed in February next year.
The Ninh Binh – Nam Dinh 220kV transmission line, which began to be constructed in August, is expected to be completed in August 2017.
In 2017, the NPMB will launch construction of the Thuong Tin – Ha Tay 500kV transmission line with the aim of completing it in the second quarter of 2018.