Accordingly, the Branch will lend Nuoc Trong Hydropower Joint Stock Company nearly VND 200 billion in the period of 15 years, of which the period of grace is 3 years.
Nuoc Trong hydropower project is a part of the Project on Nuoc Trong reservoir, which is implemented in Son Bao commune, Son Ha district. This hydropower project which has the total investment of VND 303 billion has the installation capacity of 16.5 MW, the annual power output of 10 million kWh.
Constructed since May, 2008, this project has now been basically completed with the foundation excavation and is expected to generate power in April, 2011.