Dac Lac: Start constructing IaHiao hydropower project 3
Thứ ba, 28/4/2009 | 16:00 GMT+7
On April 3, IaHiao Hydropower Company 3 (in Ea Sol commune, Ea H’Leo district) which is invested by 586 Traffic Structure Construction Joint Stock Company has been started constructing.
The hydropower plant which has the designed capacity of 4 MW and two units is built on an area of 15 ha with the entire investment of VND 78 billion. As estimated, it will be completed and put into operation in early 2011.
After operating this hydropower plant, 586 Traffic Structure Construction Joint Stock Company will erect two more hydropower plants in IaHiao river system with the designed capacity of about 10 MW.
Theo: From The Youth