Overall plan of Duyen Hai-Tra vinh Power Center

Thứ năm, 1/11/2007 | 00:00 GMT+7

According to the Ministry of Industry and Commerce, Duyen Hai-Tra Vinh Power Center has been approved to install the capacity of 4,400 kWh, including 3 projects on coal-fired thermal companies. Duyen Hai Power Company No.1 and No.2 Project will have the capacity of 2x 600MW each, and the constructing period will be in 2012-2013 and 2014-2015 respectively. Duyen hai Power Company No.2 possesses the capacity of 2x 1000MW, carried out in 2016-2017 period.

The major material resource for Duyen Hai Power Center is 8.9 million ton of coal imported annually. The subresource is 10,000 ton of FO/DO oil a day extracted from domestic or overseas oil-welling factories.

 